America

fiber optic transmission line,power transmission line,adss cable,opgw cable

Recommended

  • GL FIBER,ADSS,ADSS fiber cable,adss optical cable
    Our team is on the ground in Argentina, providing technical guidance and support for the installation of GL FIBER’s ADSS cables and fittings! From manufacturing to real-world implementation, we ensure every step meets the highest standards of quality and reliability. This video captures our experts working closely with local partners to achieve a seamless and successful deployment. Not just in China, GL FIBER’s cables are trusted and used in over 200 countries worldwide! Wherever you are, we deliver excellence and professional support.
    2025-08-26
  • opgw,opgw wire,opgw conductor,opgw fiber
    As a leading OPGW factory with over 21 years of expertise, GL FIBER successfully delivered a 268KM OPGW (Optical Ground Wire) project in Nigeria, showcasing our end-to-end OPGW solution capabilities—from custom design to seamless installation.
    2025-05-06
  • fiber cable,optical cable,fiber optic cable,optical fiber cable
    2025, GL FIBER & High-Performance Fiber Optic Network Deployment in [Afghanistan].
    2025-03-01

SUMINISTRO DE BIENES Y SERVICIOS CONEXOS PARA LINEA DE TRANSMISION EN 138 KV-Nicaragua

SUMINISTRO DE BIENES Y SERVICIOS CONEXOS

PARA LINEA DE TRANSMISION EN 138 KV LA ESPERANZA – BLUEFIELDS

Bid No.:LPI-003-2023-PASTEN-ENATREL

Issued on: Augest 26, 2023


This document is part of the Construction Project of the La Substation Expansion Esperanza, Bluefields Substation at 138 kV and La Esperanza-Bluefields Transmission line at 138 kV.

The project consists of establishing the connection between the La Esperanza substations and the new Bluefields Substation through approximately 68 km of Transmission Line at 138KV in simple circuit. For the construction of this transmission line, structures have been planned in lattice towers for the sections where the line crosses mountainous areas, cross-country and right-of-way via.

The design of the junction point to open the 69KV Transmission Line will also be included.